2015~2019年河南省输变电工程造价水平及变动因素分析

作者:李大鹏 康艳芳 郭晓菡 牛鑫 出版日期:2020年12月 报告页数:20 页 报告大小: 报告字数:11841 字 所属丛书:河南蓝皮书 所属图书:河南能源发展报告(2021) 浏览人数: 下载人数:

文章摘要:工程造价管控水平是造价管理能力的重要体现,本文针对河南省2015~2019年110~500千伏输变电工程样本,开展全省输变电工程造价水平及变动原因分析,梳理了近几年输变电工程造价水平变化态势及相关费用占比情况,从价格因素、技术因素、外部环境因素三个方面详细研究了上述因素对输变电工程造价变化的影响,指出材料、地方建材及人工费价格的提高,大容量主变、大截面导线及户内站应用比例的上升,以及政策及技术处理等外部费用的增加,是河南省输变电工程造价水平总体小幅... 展开

文章摘要:工程造价管控水平是造价管理能力的重要体现,本文针对河南省2015~2019年110~500千伏输变电工程样本,开展全省输变电工程造价水平及变动原因分析,梳理了近几年输变电工程造价水平变化态势及相关费用占比情况,从价格因素、技术因素、外部环境因素三个方面详细研究了上述因素对输变电工程造价变化的影响,指出材料、地方建材及人工费价格的提高,大容量主变、大截面导线及户内站应用比例的上升,以及政策及技术处理等外部费用的增加,是河南省输变电工程造价水平总体小幅上升的主要原因。

收起

Abstract:The level of project cost management and control is an important manifestation of cost management capabilities. Based on the samples of 110-500 kV transmission and transformation projects in Henan Province from 2015 to 2019,this article conducts the analysis of cost levels and change reasons in the power transmission and transformation projects,summarizes the changing situation of the cost level and the proportion of relevant expens... 展开

Abstract:The level of project cost management and control is an important manifestation of cost management capabilities. Based on the samples of 110-500 kV transmission and transformation projects in Henan Province from 2015 to 2019,this article conducts the analysis of cost levels and change reasons in the power transmission and transformation projects,summarizes the changing situation of the cost level and the proportion of relevant expenses of power transmission and transformation projects in recent years.The impact of price factors,technical factors,and external environmental factors on changes in the cost of power transmission and transformation projects has been studied in detail.The increase in prices of materials,local building materials and labor costs,as well as the increase usage of large-capacity main transformers,large cross-section wires,and indoor power stations,as well as the increase in external costs such as policy and technical processing,are the main reasons for the slight increase in the overall cost of power transmission and transformation projects in Henan Province.

收起

作者简介

李大鹏:李大鹏,工学学士,国网河南省电力公司经济技术研究院高级工程师,研究方向为电力工程造价管理及电网公司成本管理与控制。

康艳芳:康艳芳,经济学博士,国网河南省电力公司经济技术研究院经济师,研究方向为电网工程技术与经济。

郭晓菡:郭晓菡,管理学硕士,国网河南省电力公司经济技术研究院经济师,研究方向为电网工程技术与经济。

牛鑫:牛鑫,工程硕士,国网河南省电力公司经济技术研究院高级工程师,研究方向为电网工程技术与经济。